Rock Drilling

Ford Woodhaven

Multiple Press Pits completed with 4 total mobilizations

20" diameter Tie Rod Sleeves installed with 1" centerline tolerance

4'-0" & 4'-6" Caisson diameters

Drill depth up tp 65' 

8" to 15' Rock Sockets through 15,000 PSI limestone bedrock

Engineered Equipment Pick Plan for each phase of work

All work completed indoors with low overhead restrictions

Worked double shifts to meet owners schedule

78 Caissons and 48 Tie Rod Sleeves Completed to Date

Ford Woodhaven Stamping Plant